Connect with Us

Awards and Recognition

Saudi-Aramco-Logo

2019

No Objection Letter

Hawiyah Gas Plant Early Site Preparation Works

Mcdermott-Logo

2018

Certificate of Appreciation

D6896-SOW01-001-00(6600018863) Installation of 30″ pipeline for SAFANIYAH Trunk Line #13 includes Welding, NDT, Test- ing & Pre commissioning. Tie in of Trunk Line 13 to the existing Header No. 3, 4, 5 & 6 during SFNY. Field Shutdown.

Sdmdc-Logo

2018

Certificate of Appreciation

Waste & Cleaning Yard Project Provide procurements, supervision, man- agement, materials, manpower including transportation, food and accommodation, equipment, tools and tackles for the exe- cution of project.

Saudi-Aramco-Logo

2018

Certificate of Appreciation

Jazan IGCC Power Block Division Successful completion of Sub-Stations SS-229 & SS-429 Civil, Electro-Mechanical works.

Sharq-logo

2017

Certificate of Appreciation

A & B Bagging Machine Replacement Project

Saudi-Aramco-Logo

2017

Certificate of Appreciation

SS – 229 & SS – 429 Civil Works

Kemya-logo

2017

Certificate of Appreciation

Installation of cement lined Pipe Spool (sea water line) LLDPE plant during Kemya Turn- around 2017.

The scope includes Procurement, Pre-fabrica- tion, Cement lining, Painting, Transportation, installation and inspection.

Saudi-Aramco-Logo

2016

No Objection Letter

Civil Works Subcontractor Award

Saudi Aramco Contractor with SAP# 10042225

Petro-Rabigh-logo

2016

No Objection Letter

Carry out the HDPE and marl paving works

Contract No. 6600028401 (IK)

Daewoo-EC-logo

2016

Appreciation Letter

Temporary facilities works for Package-12 of Jazan Refinery & Terminal Project

Scope includes Engineering, Procurement, Site Preparation, Fabrication of Buildings, Transportation, Electrical Works, Plumbing Work, Fire Fighting Work & HVAC work etc.

Petrofac-logo

2016

Certificate of Appreciation

Temporary facilities civil, mechanical work as a Subcontractor for Common Utilities and Tank farm Packages – Rabigh Phase II Refin- ing and Petrochemical Project, Contract # 6600028287. Scope includes Engineering, Procurement, Site Preparation, Fabrication of Buildings, Transportation, Electrical Works, Plumbing Work, Fire Fighting Work & HVAC work etc.

samsung-logo

2016

No Objection Certificate

Saudi Aramco Third Party Congeneration Projects.

Saudi-Aramco-Logo

2016

No Objection Letter

Subcontract portion of the work of Onshore

Contract No. 6600035821 (OOK) & 6600035804 (IK), LUMP SUM Scope for Safa- niya, Berri, Marjan and Zuluf Facilities (BI-00799)

Dayim-punj-lloyd-logo

2016

Recognition Certificate

Temporary facilities work including Site Preparation, Fabrication & Installation of Temporary facility Building all associated works for yanbu Export Refinery Project, Package – SP Offsite Pipeline Package.

Dayim-punj-lloydsatorp-logo

2016

Recognition Certificate

Temporary facilities work including Site Preparation, Fabrication & Installation of Two Storeyed Temporary facility Building includ- ing all associated Electrical, Plumbing work, Fire-Fighting & HVAC Works for Jubail Export Refinery Project, Package – 9 Port tank Farm & Loading facilities located inside King Fahd Industrial Port.

Daewoo-EC-logo

2016

Appreciation Letter

Temporary facilities civil, mechanical works form phace #1 to phace #4 for Saudi Aramco Jazan Refinery & Terminal project PKG 12.

Scope includes Engineering, Procurement, Site Preparation, Fabrication of Buildings, Transportation, Site preparation Works, In- stallation of Fabricated Buildings, Electrical Works, Plumbing Work & HVAC work etc.

advanced-logo

2016

Appreciation Certificate

Plant Maintenance & Modification works, Construction of Logistic Building, Ware house Building Construction & Road works for Ad- vanced Petrochemical Co., Jubail.

Scope includes Engineering, Procurement, Site preparation, Fabrication of Buildings, Transportation, Maintenance & Modification works, Construction of Logistic Building, Ware House Building & Road works, Electri- cal, Plumbing, Firefighting & HVAC work etc.

Saudi-Aramco-Mcdermott-logo

2016

Appreciation Certificate

Civil and MEP Construction works at Manifa Onshore Drill Sites DS 13 and DS 25 pertain- ing to Subcontract D6728-SC002C.

Saudi-Aramco-Logo

2015

No Objection Letter

Execute Onshore MEP Works at Manifa Causeway.

Contract No. 6600018863 (IK) & 6600018864 (OOK), Offshore Long Term Agreement; Offshore facilities Procurement, Fabrication, Trans & Installation, CRPO 6510590729 (IK) & 6510590786 (OOK) BI-10-03042

Saudi-Aramco-Logo

2014

No Objection Letter

Subcontract agreement for Execution of On- shore Civil Works at Manifa Causeway.

Contract No. 6600018863 (IK) & 6600018864 (OOK), LTA/CRPO #6510590786 (OOK) & 6510590729 (ΙΚ) BI-10-03042 Manifa 460/470 Deck and Associated Facilities.

Satorp-logo

2013

Certificate of Appreciation

Temporary Office Facility & Camp Facility work for JUBAIL EXPORT REFINERY COM- PLEX PACKAGE -6 Tank Farm PROJECT.

The scope includes Engineering, Design, Preparation of all the drawings for all building & utilities, Electrical & Mechanical works, Car Parking, Road & Commissioning etc.

Daelim-Sabic-logo

2012

Mechanical Completion Certificate

Early work for Building and temporary Facili- ties for Saudi Elastomers Project in Al-Jubail, KSA.